Mobile menu MENU

Other tasks & projects

Beside the external projects and training & education there are some other tasks and projects that I carry out.

 

HagaZiekenhuis | June 2016 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the HagaZiekenhuis several EPR's were implemented. After the go live, montly content-updates are performed. Because all the EPR's were already in use, a simple transfer from ChipSoft to the HagaZiekenhuis production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). During acceptance testing intensive second line support was provided to solve problems that occurred due to the content-update. In case of accepting the content-update, HagaZiekenhuis installs the same content-update on the production environment. This procedure repeats itself every month.

Jeroen Bosch Ziekenhuis | June 2016 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the Jeroen Bosch Ziekenhuis several EPR's were implemented. After the go live, montly content-updates are performed. Because all the EPR's were already in use, a simple transfer from ChipSoft to the Jeroen Bosch Ziekenhuis production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). During acceptance testing intensive second line support was provided to solve problems that occurred due to the content-update. In case of accepting the content-update, Jeroen Bosch Ziekenhuis installs the same content-update on the production environment. This procedure repeats itself every month.

Erasmus MC | March 2016 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure

At Erasmus Ziekenhuis several EPR's are going to be implemented. The transfer of EPR content from ChipSoft to the development environment will be executed by using the DTAP (development, testing, acceptance, production procedure). The content will be extracted from ChipSoft and then imported in the development environment.

Elkerliek | November 2015 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the Elkerliek hospital several EPR's were implemented. After the go live, montly content-updates are performed. Because all the EPR's were already in use, a simple transfer from ChipSoft to the Elkerliek production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). During acceptance testing intensive second line support was provided to solve problems that occurred due to the content-update. In case of accepting the content-update, Elkerliek installs the same content-update on the production environment. This procedure repeats itself every month.

Maastro Clinic | August 2015 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the Maastro Clinic several EPR's were implemented. After the go live, montly content-updates are performed. Because all the EPR's were already in use, a simple transfer from ChipSoft to the Maastro Clinic production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). During acceptance testing intensive second line support was provided to solve problems that occurred due to the content-update. In case of accepting the content-update, Maastro Clinic installs the same content-update on the production environment. This procedure repeats itself every month.

Waterland Ziekenhuis | November 2014 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the Waterland Ziekenhuis several EPR's were implemented. After the go live, montly content-updates are performed. Because all the EPR's were already in use, a simple transfer from ChipSoft to the Waterland Ziekenhuis production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). During acceptance testing intensive second line support was provided to solve problems that occurred due to the content-update. In case of accepting the content-update, Waterland Ziekenhuis installs the same content-update on the production environment. This procedure repeats itself every month.

Laurentius Ziekenhuis | June - September 2014

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure

At Laurentius Ziekenhuis several EPR's were implemented. The transfer of EPR content from ChipSoft to the development environment was executed by using the DTAP (development, testing, acceptance, production procedure). The content was extracted from ChipSoft and imported in the development environment. After reviewing the best-practice EPR's, the same procedure was used to transfer EPR content from ChipSoft to the production environment.

Rivas Zorggroep | April 2014 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the Rivas Zorggroep several EPR's were implemented. After the go live, montly content-updates are performed. Because all the EPR's were already in use, a simple transfer from ChipSoft to the Rivas Zorggroep production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). During acceptance testing intensive second line support was provided to solve problems that occurred due to the content-update. In case of accepting the content-update, Rivas Zorggroep installs the same content-update on the production environment. This procedure repeats itself every month.

Laurentius Ziekenhuis | February - May 2014

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure

At Laurentius Ziekenhuis several EPR's were implemented. The transfer of EPR content from ChipSoft to the development environment was executed by using the DTAP (development, testing, acceptance, production procedure). The content was extracted from ChipSoft and imported in the development environment. After reviewing the best-practice EPR's, the same procedure was used to transfer EPR content from ChipSoft to the production environment.

Laurentius Ziekenhuis | November 2013 - February 2014

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure

At Laurentius Ziekenhuis several EPR's were implemented. The transfer of EPR content from ChipSoft to the development environment was executed by using the DTAP (development, testing, acceptance, production procedure). The content was extracted from ChipSoft and imported in the development environment. After reviewing the best-practice EPR's, the same procedure was used to transfer EPR content from ChipSoft to the production environment.

Lievensberg Ziekenhuis | October 2013 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the Lievensberg Ziekenhuis / Franciscus Ziekenhuis several EPR's were implemented. After the go live, montly content-updates are performed. Because all the EPR's were already in use, a simple transfer from ChipSoft to the Lievensberg Ziekenhuis / Franciscus Ziekenhuis production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). During acceptance testing intensive second line support was provided to solve problems that occurred due to the content-update. In case of accepting the content-update, Bravis installs the same content-update on the production environment. This procedure repeats itself every month.

Franciscus Ziekenhuis | October 2013 till now

Manager (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the Lievensberg Ziekenhuis / Franciscus Ziekenhuis several EPR's were implemented. After the go live, montly content-updates are performed. Because all the EPR's were already in use, a simple transfer from ChipSoft to the Lievensberg Ziekenhuis / Franciscus Ziekenhuis production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). During acceptance testing intensive second line support was provided to solve problems that occurred due to the content-update. In case of accepting the content-update, Bravis installs the same content-update on the production environment. This procedure repeats itself every month.

Rijnstate | August 2013

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At the time that two content-updates were executed, Rijnstate visited Amsterdam to discuss the procedure. Problems with the content-updates were discussed and future vision of ChipSoft about content-updates was discussed. It was decided to postpone future content-updates until the procedure is more stable.

Rijnstate | April 2013

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At Rijnstate EPR's of oncology and gastro-entrology were implemented after several months of go live a content-update of the two EPR's was executed. Because all two EPR's were already in use, a simple transfer from ChipSoft to the Rijnstate production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). Rijnstate tested the new content and on acceptance the content was extracted from ChipSoft and imported in the production environment. Afterwards intensive second line support was provided to solve problems that occurred due to the content-update.

Rijnstate | January 2013

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure - content-update

At Rijnstate 18 EPR's were implemented after several months of go live a content-update of the 18 EPR's was executed. Because all 18 EPR's were already in use, a simple transfer from ChipSoft to the Rijnstate production environment was out of the question. A transfer of EPR content from ChipSoft to the acceptation environment was executed by using the DTAP (development, testing, acceptance, production procedure). Rijnstate tested the new content and on acceptance the content was extracted from ChipSoft and imported in the production environment. Afterwards intensive second line support was provided to solve problems that occurred due to the content-update.

VieCuri Medisch Centrum | November 2012

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure

At VieCuri several EPR's were implemented. The transfer of EPR content from ChipSoft to the development environment was executed by using the DTAP (development, testing, acceptance, production procedure). The content was extracted from ChipSoft and imported in the development environment. After reviewing the best-practice EPR's, the same procedure was used to transfer EPR content from ChipSoft to the production environment.

Zeelandcare | October 2012

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure

At Zeelandcare several EPR's were implemented. The transfer of EPR content from ChipSoft to the development environment was executed by using the DTAP (development, testing, acceptance, production procedure). The content was extracted from ChipSoft and imported in the development environment. After reviewing the best-practice EPR's, the same procedure was used to transfer EPR content from ChipSoft to the production environment.

LUMC | September - December 2012

Lead consultant (DTAP)

Development, Testing, Accepting, Production procedure

In a hospital several software environments are used: development environment for developing new features, test environment for testing new features, acceptation environment for accepting new features by end users, a production environment that is used to store real-time data produced in the healthcare setting. These new features are transferred manually to each environment, this is labour intensive and in each transfer errors can be made. Together with the LUMC efforts were made to computerize the step from acceptation environment to the production environment. Unfortunately the project was cancelled due to conflicting internal priorities at the LUMC and ChipSoft. This project may be continued at a later stage.

Lievensberg Ziekenhuis | September 2013

Lead consultant (Consultancy)

Oncology suite

During the implementation of the oncology EPR oncologists visited ChipSoft to discuss the important work processes regarding cytostatics. The goal was to innovate the oncology, cytostatics and day treatments as a whole. Due to the complex processes it is needed to continuously evaluate the best-practice and improve where appropriate. In the end it should be even a more integrated EPR suite, in which the EPR, cytostatics and day treatments are even better documented and easily accessible. The end user should see at a glance the treatment plan of the patient and see what's to come and see what has been done.

Franciscus Ziekenhuis | September 2013

Lead consultant (Consultancy)

Oncology suite

During the implementation of the oncology EPR oncologists visited ChipSoft to discuss the important work processes regarding cytostatics. The goal was to innovate the oncology, cytostatics and day treatments as a whole. Due to the complex processes it is needed to continuously evaluate the best-practice and improve where appropriate. In the end it should be even a more integrated EPR suite, in which the EPR, cytostatics and day treatments are even better documented and easily accessible. The end user should see at a glance the treatment plan of the patient and see what''s to come and see wha

AMC | November 2012

Lead consultant (Consultancy)

Medical Informatics Symposium

The Health Informatics Symposium offers students of this study to meet companies in the IT healthcare sector. During this symposium students could ask us anything about working at ChipSoft. Also demonstrations of the software were given to give an impression of the best-practice EPR.

UMC Utrecht | August 2012

Lead consultant (Consultancy)

Consultancy to solve problems regarding context

Several supportcalls were submitted by the LUMC. These supportcalls reported problems with context, wrong information was presented in the EPR of another patient, or healthcare professionals thought they had selected patient A and the EPR showed patient B. All the problems were investigated on site and software fixes were rapidly developed and released to fix the problems. Also end user instructions were given in an effort to eliminate these kind of problems. Although the UMCU had the same EPR's, problems were not reported so working methods of the LUMC were also investigated and some were tweaked.

LUMC | August 2012

Lead consultant (Consultancy)

Consultancy to solve problems regarding context

Due to the supportcalls of the LUMC regarding problems with context (wrong information was presented in the EPR of another patient, or healthcare professionals thought they had selected patient A and the EPR showed patient B) the UMCU was also visited. All the problems were investigated on site and it was determined that the problems reported by the LUMC were not applicable to the UMCU. After investigation of working methods it was concluded that both hospitals worked slightly different with regard to EPR's.

Lievensberg Ziekenhuis | March 2012

Lead consultant (Consultancy)

Consultancy about EPR's, forms and (DTAP) Development, Testing, Accepting, Production procedure

During the implementation of the hospital-wide EPR Lievensberg had some questions about the techniques that are used to transfer the content and the consequences for EPR maintenance. We explained the do's and don'ts and impact of changes made by Lievensberg regarding to the best-practice EPR. The guidelines for EPR development and form development were also discussed.

Slingeland Ziekenhuis | January 2012

Lead consultant (Consultancy)

Consultancy about EPR's and forms

Slingeland had developed their own EPR's and forms to facilitate healthcare professionals, however the complexity was growing exponentially. We gave information about how we solved the problems in the best-practice Slingeland was facing. Also some tips and tricks were given to reduce the complexity of the EPR's and forms.

AMC | September 2011

Lead consultant (Consultancy)

Medical Informatics Symposium

The Health Informatics Symposium offers students of this study to meet companies in the IT healthcare sector. During this symposium students could ask us anything about working at ChipSoft. Also demonstrations of the software were given to give an impression of the best-practice EPR.

Design by M.H. de Groot & W3layouts external link | Copyright 2014-2024 M.H. de Groot All rights reserved | Last modified September 20, 2016 at 20:25:40 external link | Unique page views 991 views